Excavation and lagging work continues...
X
Excavation and lagging work continues...
X
Excavation and lagging work continues...
X
Excavation and lagging work continues...
X
Excavation and lagging work continues...
X
Excavation and lagging work continues...
X
Excavation and lagging work continues...
X
Excavation and lagging work continues...
X
Excavation and lagging work continues...
X
Excavation and lagging work continues...
X
Excavation and lagging work continues...
X
Excavation and lagging work continues...
X
Excavation and lagging work continues...
X
Excavation and lagging work continues...
X
Excavation and lagging work continues...
X
Test tiebacks have been approved.
X
Shaving of caissons on the west side underway.
X
Test tiebacks have been approved.
X
North Side Wood Fence Complete. Tieback Placement Continues.
X
North Side Wood Fence Complete. Tieback Placement Continues.
X
North Side Wood Fence Complete. Tieback Placement Continues.
X
Southwest View of the Construction Site at Everhome.
X
Lagging Work at the Entrance Along the East Side.
X
Tieback Installation Continues on the South Side.
X
All Tiebacks are Complete. Additional Excavation has Started.
X
All Tiebacks are Complete. Additional Excavation has Started.
X
All Tiebacks are Complete. Additional Excavation has Started.
X
Excavation Reinitiated to Reach the Final Geodetic Depth.
X
Excavation Reinitiated to Reach the Final Geodetic Depth.
X
Excavation Reinitiated to Reach the Final Geodetic Depth.
X
NOW UNDER CONSTRUCTION: Continuing with Excavation and Tieback Welding to Reach Final Depth.
X
NOW UNDER CONSTRUCTION: Continuing with Excavation and Tieback Welding to Reach Final Depth.
X
NOW UNDER CONSTRUCTION: Continuing with Excavation and Tieback Welding to Reach Final Depth.
X
UNDER CONSTRUCTION: Lagging and Excavation is Ongoing
X
UNDER CONSTRUCTION: Lagging and Excavation is Ongoing
X
UNDER CONSTRUCTION: Lagging and Excavation is Ongoing
X
UNDER CONSTRUCTION: Lagging and Excavation is Ongoing
X
UNDER CONSTRUCTION: Lagging and Excavation is Ongoing
X
UNDER CONSTRUCTION: Lagging and Excavation is Ongoing
X
Installation of Walers And Lagging Work Continues
X
Installation of Walers And Lagging Work Continues
X
Installation of Walers And Lagging Work Continues
X
Trench Cutting to Complete Lagging on South Side.
X
Trench Cutting to Complete Lagging on South Side.
X
Trench Cutting to Complete Lagging on South Side.
X
Second Row of Cross Braces Installed on the Northwest Corner.
X
Additional Lagging Below Tiebacks on Northwest side.
X
Additional Lagging Below Tiebacks on Northwest side.
X
Southwest Corner, Shaving of Piles Continues.
X
Bulk Excavation Ongoing.
X
Bulk Excavation Continues.
X
Southwest Corner, Shaving of Piles Continues to Allow for Second Cross Braces.
X
Bulk Excavation Continues.
X
Bulk Excavation Continues.
X
Preparation for Rakers and Raker Pad Underway.
X
Preparation for Rakers and Raker Pad Underway.
X
2nd row of Corner Braces on the Southwest Side completed.
X
Excavating for Crane Pad.
X
Excavating for Crane Pad.
X
Excavating for Crane Pad.
X
Crane Base Installation Started
X
Crane Base Installation Started
X
Crane Base Installation Started
X
Verticals Formed with Footings in Place on P3 Level
X
Preparing forms for additional verticals for P3 Level
X
Water proofing the southwest corner, followed by rebar placement and the footings to allow the erection of the perimeter walls
X
Demising wall at the end of P3 to P2 level, formed and completed
X
Detailed excavation for footings on north side of P3
X
Footing forms for P3 Mechanical and Geo-thermal Rooms
X
Trenching for central area footings on P3
X
Preparing Forms for the Geo-thermal Room
X
Additional Vertical Forms Prepped on P3
X
View looking east showing progress of footings and verticals
X
P3 Termination Wall Connected to Geo-thermal Room Wall
X
Waterproofing Started on the East Side
X
Wall Forms Erected on the South Side
X
Waterproofing and rebar in place for formwork on the southeast corner.
X
P3 verticals are all completed, showing rackers and cross braces on the northwest side.
X
Two P2 verticals erected, waterproofing and rebar in place on south side.
X
Forming perimeter walls on the south and east sides.
X
Forming the north wall of the geo-thermal room on P3.
X
Placing rebar in front of waterproofing on the south side.
X
Geo-thermal room perimeter on P3 is complete
X
Rebar for P2 verticals have been assembled
X
Forming of the sump pit for the east block has started
X
Main sump pit for East Block installed and surrounded by U-Fill
X
Geo-thermal work on P3 continues
X
Geo-thermal room strip footings extended and forms for walls are being erected
X
Bore holes repaired and being connected on P3 level
X
Strip footings and north side wall forms continue for geo-thermal room
X
Geo-thermal work on P3 continues
X
Eastern edge of the geo-thermal room and applicable strip footings
X
East end of geo-thermal room completed
X
Remaining lagging work on northeast side now continues
X
Waterproofing on P3 to P2 Demising wall complete
X
Bore hole circuits penetrated into geo-thermal room
X
Bore holes connected to the main circuit loop
X
Circuit loops positioned in trenches under P3
X
Final preparation for Slab on Grade
X
Final preparation for Slab on Grade
X
Final preparation for Slab on Grade
X
3/4" stone now being distributed on P3 in advance of Slab-On-Grade
X
3/4" stone now being distributed on P3 in advance of Slab-On-Grade
X
3/4" stone now being distributed on P3 in advance of Slab-On-Grade
X
Slab On Grade (SOG) P3 Pour 1 completed
X
P3 Level, Preparation of Pour 2 in the foreground and completed Pour 1 in the distance
X
P3 Pour 2 sub-grade preparation complete
X
Formwork for P2 Structural Slab underway
X
Geo-thermal circuit D loop is being laid on P2 trenches
X
Formwork for P2 capitals on columns underway
X
Perimeter wall forms have arrived to site
X
North Block east stair well, footings being poured
X
South East side perimeter wall rebar placement has started
X
Erecting column forms from P1 to Ground on the South East side.
X
Detailed excavation for EAST Block Elevator Pit ready to receive the pre-formed rebar assembly (shown in the image)
X
Erecting north wall form above Geo-Thermal Room from P2 to P1
X
The final geo-thermal loop (B) being grouted and cleared for fusing to begin
X
Perimeter wall forms in place for the Northside of the site at the retaining wall, P1 to ground
X
Rebar placement around the east stairwell for the North Block started, Level 2 to 1. Trenching for the geo-thermal loops in the foreground
X
Final geo-thermal loop complete and pressure tested. Trenches with the main loop pipes are being back filled with 3/4 stone
X
Stone also being spread out over the remaining sections in preparation for Slab On Grade (SOG)
X
Cross braces on the southwest corner cut and being removed
X
Conduit and rebar for the west side completed, awaiting concrete
X
Strip footings on the north and east side poured. All footings are now complete at Everhome
X
West side structural slab fully poured
X
Additional 3/4” stone received for spreading in preparation of Slab On Grade (SOG) around the crane base
X
P2 Level Waterproofing on the north side completed. Now preparing for rebar placement for the perimeter wall
X
Rebar work continues on the southeast side, from P1 to Ground
X
Completed Slab On Grade (SOG) between the North perimeter wall and the Geo-thermal Room
X
Preparation to initiate shotcrete along the North perimeter wall, towards the East perimeter wall
X
Completed Slab On Grade (SOG) around the crane base
X
Prepping for Concrete Pour at P1 around the crane base
X
Waterproofing progressing along the North Wall, heading eastwards
X
Spreading stone in preparation of the Slab On Grade (SOG) for the North East portion
X
August 4th - All SOG (Slab On Grade) now complete!
X
August 4th - All SOG (Slab On Grade) now complete!
X
August 4th - All SOG (Slab On Grade) now complete!
X
August 28th - P1 Structural Slab poured that will act as base for the soil in the Central Courtyard
X
August 28th - Waterproofing on the East Perimeter Wall started, P1 to Ground
X
August 28th - Rebar installed for the North and East Perimeter Wall Sections showcasing the duct bank for Electrical Utility on the East Face
X
August 29th - P1 decking continues along the northern side of the property from West to East
X
August 29th - Perimeter Wall of the North and East sections completed, P1 to Ground
X
August 29th - South Perimeter Wall Forms are starting to be placed from the east side, P1 to Ground
X
August 30th - Central section form work started, P1 to Ground
X
August 30th - Southwest Air Exhaust forming started, P1 to Ground
X
August 30th - Stripping of the South Perimeter wall at the East Side, P1 to Ground
X
September 1st - North Perimeter Wall stripped and moved east for the next section
X
September 1st - Tie rods welded to the East Perimeter wall piles
X
September 1st - Central interior wall around the crane base formed from P1 to Ground
X
September 5th - Rebar and conduit work continues on the structural slab next to the North Perimeter Wall
X
September 5th - Decking for P1 structural slab continues along the northern side of the site
X
September 5th - Rebar placement on the East Perimeter Wall continues, from P1 to Ground
X
September 6th - Aerial view capturing site progress at Everhome Markham
X
September 6th - Aerial view capturing site progress at Everhome Markham
X
September 8th - P1 structural slab poured from N6 to N9 (west to east), along the North Perimeter Wall, south to the Geo-Thermal wall
X
September 8th - Rebar along the East Perimeter Wall complete for shotcrete application, P1 to Ground
X
September 8th - Stripping of the forms for the southwest corner air shaft, P1 to Ground
X
September 18th - Decking, rebar and conduit placement continues along the Northeast side of the site
X
September 18th - Shotcrete used to complete the Southeast corner and the entire East Perimeter Wall
X
September 18th - Structural slab pour on the north east
X
September 22nd - Rebar placement continues to the garage door entry below the North Block
X
September 22nd - Structural slab pour on the Northside of the P1 Ramp
X
September 22nd - Piping installation continues below grade, P3 and P2
X
September 26th - Structural slab along the north side, mid-span formed, next to the ramp on the south section
X
September 26th - Bottom rebar placement continues and conduit work started along the Northeast side for ground floor slab
X
September 26th - Forms are being placed around the EAST BLOCK elevators
X
October 2nd - Stripping of the Stairwell and EAST Block Elevators completed
X
October 2nd - Deck forming for the Northeast corner complete and rebar placement continues
X
October 2nd - Extensive rebar placement continues for the northeast area in anticipation of Gas Connection
X
October 25th - Decking work continues on the Ground Floor around the crane base
X
October 25th - Storm Water Tank deck continues on the Northwest side in preparation for Site Service Connections
X
October 25th - Northwest Perimeter wall forming continues to Ground Floor
X
October 27th - Decking on the West side continues for the ground floor slab
X
October 27th - Waterproofing, and rebar placement completed on the North side, in preparation for Shotcrete to follow
X
October 27th - Air shaft at the Northeast corner formed for the south and west walls
X
November 20th - Slab for the Southwest corner has been completed
X
November 20th - Decking completed between the Central Courtyard and South Block, ready to receive rebar and conduit
X
November 20th - Rebar and conduit work has started on the Southwest corner
X
December 6th - Rebar and Stud Rail placement continues on the Southwest side of Everhome
X
December 6th - Wall forms and rebar in place for Storm Water Tank pour
X
December 6th - North perimeter wall Shotcrete completed
X
December 8th - First pour of the South Block ground floor section is complete
X
December 8th - Shotcrete wall stripped along the Northside of the site
X
December 8th - Stormceptor area within the Storm Water Tank completed on the Westside of the site
X
December 11th - Conduit work and top bar placement continues along the south side of the Central Courtyard in preparation for the next pour
X
December 11th - Completed the second concrete pour for the terraces related to the SOUTH Block
X
December 11th - Bottom rebar placement on the last portion of the east side of the SOUTH Block underway
X
January 30th - Portion of the ground floor slab completed on the EAST Block
X
January 30th - Additional portions of the ground floor slab to the north side of the EAST Block completed
X
January 30th - Wall form erected to pour the north side of the fire route which also encases the long term bicycle storage for homeowners at grade
X
March 6th - Scaffolding to the second level of the EAST Block started
X
March 6th - NORTH Block poured the terraces along the northern property line
X
March 6th - EAST Block retail mezzanine decking complete and rebar work started. Stair well east of the mezzanine level formed to the second level
X
March 8th - Decking for units N101 and N02 on the elevated portion of the NORTH Block has been completed. Rebar placement has started and continues
X
March 8th - Rebar placement complete up to Level 2 for Stair E on the EAST Block. Exterior formwork around the rebar to follow next, before pouring concrete
X
March 8th - Rebar placement complete up to Level 2 for Elevator 2 in the SOUTH Block. Exterior formwork to follow around the rebar, before pouring concrete
X
March 18th - EAST Block, level 2 decking started and progressing well from the south side heading north. Square columns from ground to level 2 formed and stripped
X
March 18th - Concrete pour for the lower sections related to N101 and N102 completed
X
March 18th - Rebar placement for the top section well underway with intentions to pour concrete this week
X
March 22nd - N101 and N102 top concrete pour completed
X
March 22nd - Bottom pour associated with the NORTH Block, entrance of N101 and N02 completed. Forms erected for the top concrete pour
X
March 22nd - Forms stripped to expose columns from Ground to Level 2 on the EAST Block
X
May 30 - Next Step, wall panel erection for the Kids Play Area and Movie Screening Room on level 2
X
May 30- Mesh/rebar placed on level 2 awaiting concreate pour
X
May 30 - Concrete topping completed above the Hambro Joist System
X
May 31 - EAST BLOCK : 40% Level 3 Slab Completed
X
May 31 - EAST BLOCK : 40% Level 3 Slab Completed
X
May 31 - EAST BLOCK : 40% Level 3 Slab Completed
X
June 4 - EAST BLOCK : Lower rebar placed on the balance of formwork for Level 3, from the pour break to the northern edge. Conduit and sleeve work also started.
X
June 4 - EAST BLOCK : Lower rebar placed on the balance of formwork for Level 3, from the pour break to the northern edge. Conduit and sleeve work also started.
X
June 4 - EAST BLOCK : Lower rebar placed on the balance of formwork for Level 3, from the pour break to the northern edge. Conduit and sleeve work also started.
X
June 7 - WEST BLOCK : West Block second level wall panels completed allowing the Hambro Joists for the ceiling to be erected
X
June 7 - WEST BLOCK : West Block second level wall panels completed allowing the Hambro Joists for the ceiling to be erected
X
June 7 - WEST BLOCK : Plywood base and roller bars installed in preparation of concrete pour to follow
X
June 15 - 65% of Level 4 Slab completed. Bottom rebar placement along with sleeving and conduit work continues for the balance of Level 4
X
June 15 - EAST BLOCK : Level 4, rebar, sleeving and conduit work completed in anticipation of the first pour
X
June 15 - 65% of Level 4 Slab completed. Bottom rebar placement along with sleeving and conduit work continues for the balance of Level 4
X
June 17 - Elevator lift completed on the second level of the West Block
X
June 17 - Exit stair landing poured on the Northside of the West Block
X
June 17 - Structural steel positioned as needed
X
June 18 - Rebar and sleeving progresses well for the balance of the north side of Level 4 Slab
X
June 18 - Rebar and sleeving progresses well for the balance of the north side of Level 4 Slab
X
June 18 - Verts formed from Level 4 to Level 5 on the South side of the EAST Block
X
August 29 - Decking South Block Level 2
X
August 29 - Level 3 Densglass perimeter wall facing West
X
August 29 - Stud work Level 4 started
X
September 6 - AERIAL VIEW :: Looking northwest to capture the progress of the NORTH Block with the structural steel placement
X
September 6 - EAST Block: 8th level top rebar placement has started for the first concrete pour from the south side extending north past the elevator core
X
September 6 - SOUTH Block :: 2nd Level plywood backing ready with wire mesh and girders to receive concrete topping
X
September 13 - EAST Block : Level 8 pour 1, completed, view looking East
X
September 13 - NORTH Block : Stair on the east side, prepped to receive concrete pour extending to the second level
X
September 13 - Sanitary connections below grade well underway for the SOUTH Block
X
October 24 - Decking for the Roof of the 2-Storey Penthouse Suites facing West well underway. Elevator and south stair well already erected to the Mechanical Penthouse Level.
X
October 24 - SOUTH BLOCK: 3rd level pour completed
X
October 24 - EAST BLOCK: Dens glass placement on the exterior face and Blue skin application complete along the entire rough window opening. Window track placement on the base to receive the window installation.
X
November 5 - Window installation for Levels 2 and 3 completed
X
November 5 - Window installation for Levels 2 and 3 completed
X
November 5 - Mechanical penthouse roof prepped for final concrete pour