under construction banner
Now Under
Construction

Construction Update

Click on images below

November 2022

November 24th
  –  
Preparing Forms for the Geo-thermal Room
Everhome Markham Construction
Everhome Markham Construction
Everhome Markham Construction
November 22nd
  –  
Detailed excavation for footings on north side of P3
Everhome Markham Construction
Everhome Markham Construction
Everhome Markham Construction
November 21st
  –  
Preparing forms for additional verticals for P3 Level
Everhome Markham Construction
Everhome Markham Construction
Everhome Markham Construction
November 15th
  –  
Overall Site Progress
Everhome Markham Construction
Everhome Markham Construction
Everhome Markham Construction
November 1st
  –  
CRANE NOW ERECTED
Everhome Markham Construction
Everhome Markham Construction
Everhome Markham Construction

October 2022

October 19th
  –  
CRANE BASE COMPLETE
Everhome Markham Construction
Everhome Markham Construction
Everhome Markham Construction
October 18th
  –  
Crane Base Installation Started
Everhome Markham Construction
Everhome Markham Construction
Everhome Markham Construction
October 17th
  –  
Excavating for Crane Pad
Everhome Markham Construction
Everhome Markham Construction
Everhome Markham Construction
October 7th
  –  
2nd row of Corner Braces on the Southwest Side Completed
Everhome Markham Construction
Everhome Markham Construction
Everhome Markham Construction

September 2022

September 30th
  –  
Southwest Corner, Shaving of Piles Continues to Allow for Second Cross Braces.
Everhome Markham Construction
Everhome Markham Construction
Everhome Markham Construction
September 23th
  –  
Southwest Corner, Shaving of Piles Continues.
Everhome Markham Construction
Everhome Markham Construction
Everhome Markham Construction
September 16th
  –  
Second Row of Cross Braces Installed on the Northwest Corner.
Everhome Markham Construction
Everhome Markham Construction
Everhome Markham Construction
September 7th
  –  
Trench Cutting to Complete Lagging on South Side.
Everhome Markham Construction
Everhome Markham Construction
Everhome Markham Construction
September 1st
  –  
Installation of Walers and Lagging Work Continues.
Everhome Markham Construction
Everhome Markham Construction
Everhome Markham Construction

August 2022

August 30th
  –  
UNDER CONSTRUCTION: Lagging and Excavation is Ongoing.
Everhome Markham Construction
Everhome Markham Construction
Everhome Markham Construction
August 29th
  –  
UNDER CONSTRUCTION: Lagging and Excavation is Ongoing.
Everhome Markham Construction
Everhome Markham Construction
Everhome Markham Construction
August 19th
  –  
UNDER CONSTRUCTION: Continuing with Excavation and Tieback Welding to Reach Final Depth.
Everhome Markham Construction
Everhome Markham Construction
Everhome Markham Construction
August 18th
  –  
Excavation Reinitiated to Reach the Final Geodetic Depth.
Everhome Markham Construction
Everhome Markham Construction
Everhome Markham Construction
August 15th
  –  
All Tiebacks are Complete. Additional Excavation has Started.
Everhome Markham Construction
Everhome Markham Construction
Everhome Markham Construction
August 9th
  –  
Tiebacks 50% Complete. Additional Excavation to Follow.
Everhome Markham Construction
Everhome Markham Construction
Everhome Markham Construction

July 2022

July 15th
  –  
Excavation and lagging work continues...
Everhome Markham Construction
Everhome Markham Construction
Everhome Markham Construction

June 2022

June 10th
  –  
86 Shoring Piles Complete.
Everhome Markham Construction
Everhome Markham Construction
Everhome Markham Construction

May 2022

May 27th
  –  
Shoring activities continue on the north side, next to the Radiant Montessori School.
Everhome Markham Construction

April 2022

April 23th
  –  
Completing the platform for shoring to begin.
Everhome Markham Construction
Everhome Markham Construction

March 2022

March 24th
  –  
Platform preparation at Everhome Markham underway.
Everhome Markham Construction


February 2022

February 24th
  –  
Bore hole drilling continues.
Everhome Markham Construction
Everhome Markham Construction


January 2022

January 2022
Everhome Markham Construction
Everhome Markham Construction


October 2021

October 2021
Everhome Markham Construction
Everhome Markham Construction


July 2021

July 2021
Everhome Markham Construction


June 2021

June 2021
Everhome Markham Construction
Everhome Markham Construction
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
View Looking North
X
View Looking Northeast
X
View Looking Northeast
X
Excavation and lagging work continues...
X
Excavation and lagging work continues...
X
Excavation and lagging work continues...
X
Excavation and lagging work continues...
X
Excavation and lagging work continues...
X
Excavation and lagging work continues...
X
Excavation and lagging work continues...
X
Excavation and lagging work continues...
X
Excavation and lagging work continues...
X
Excavation and lagging work continues...
X
Excavation and lagging work continues...
X
Excavation and lagging work continues...
X
Excavation and lagging work continues...
X
Excavation and lagging work continues...
X
Excavation and lagging work continues...
X
Test tiebacks have been approved.
X
Shaving of caissons on the west side underway.
X
Test tiebacks have been approved.
X
North Side Wood Fence Complete. Tieback Placement Continues.
X
North Side Wood Fence Complete. Tieback Placement Continues.
X
North Side Wood Fence Complete. Tieback Placement Continues.
X
Southwest View of the Construction Site at Everhome.
X
Lagging Work at the Entrance Along the East Side.
X
Tieback Installation Continues on the South Side.
X
All Tiebacks are Complete. Additional Excavation has Started.
X
All Tiebacks are Complete. Additional Excavation has Started.
X
All Tiebacks are Complete. Additional Excavation has Started.
X
Excavation Reinitiated to Reach the Final Geodetic Depth.
X
Excavation Reinitiated to Reach the Final Geodetic Depth.
X
Excavation Reinitiated to Reach the Final Geodetic Depth.
X
NOW UNDER CONSTRUCTION: Continuing with Excavation and Tieback Welding to Reach Final Depth.
X
NOW UNDER CONSTRUCTION: Continuing with Excavation and Tieback Welding to Reach Final Depth.
X
NOW UNDER CONSTRUCTION: Continuing with Excavation and Tieback Welding to Reach Final Depth.
X
UNDER CONSTRUCTION: Lagging and Excavation is Ongoing
X
UNDER CONSTRUCTION: Lagging and Excavation is Ongoing
X
UNDER CONSTRUCTION: Lagging and Excavation is Ongoing
X
UNDER CONSTRUCTION: Lagging and Excavation is Ongoing
X
UNDER CONSTRUCTION: Lagging and Excavation is Ongoing
X
UNDER CONSTRUCTION: Lagging and Excavation is Ongoing
X
Installation of Walers And Lagging Work Continues
X
Installation of Walers And Lagging Work Continues
X
Installation of Walers And Lagging Work Continues
X
Trench Cutting to Complete Lagging on South Side.
X
Trench Cutting to Complete Lagging on South Side.
X
Trench Cutting to Complete Lagging on South Side.
X
Second Row of Cross Braces Installed on the Northwest Corner.
X
Additional Lagging Below Tiebacks on Northwest side.
X
Additional Lagging Below Tiebacks on Northwest side.
X
Southwest Corner, Shaving of Piles Continues.
X
Bulk Excavation Ongoing.
X
Bulk Excavation Continues.
X
Southwest Corner, Shaving of Piles Continues to Allow for Second Cross Braces.
X
Bulk Excavation Continues.
X
Bulk Excavation Continues.
X
Preparation for Rakers and Raker Pad Underway.
X
Preparation for Rakers and Raker Pad Underway.
X
2nd row of Corner Braces on the Southwest Side completed.
X
Excavating for Crane Pad.
X
Excavating for Crane Pad.
X
Excavating for Crane Pad.
X
Crane Base Installation Started
X
Crane Base Installation Started
X
Crane Base Installation Started
X
CRANE BASE COMPLETE
X
CRANE BASE COMPLETE
X
CRANE BASE COMPLETE
X
CRANE NOW ERECTED
X
CRANE NOW ERECTED
X
CRANE NOW ERECTED
X
Overall Site Progress
X
Verticals Formed with Footings in Place on P3 Level
X
Waterproofing of P3
X
Preparing forms for additional verticals for P3 Level
X
Water proofing the southwest corner, followed by rebar placement and the footings to allow the erection of the perimeter walls
X
Demising wall at the end of P3 to P2 level, formed and completed
X
Detailed excavation for footings on north side of P3
X
Footing forms for P3 Mechanical and Geo-thermal Rooms
X
Trenching for central area footings on P3
X
Preparing Forms for the Geo-thermal Room
X
Additional Vertical Forms Prepped on P3
X
View looking east showing progress of footings and verticals
X