under construction banner
Now Under
Construction

Construction Update

Click on images below

March 2024

March 22nd
  –  
N101 and N102 top concrete pour completed
Everhome Markham Construction
Everhome Markham Construction
Everhome Markham Construction
March 18th
  –  
EAST Block, level 2 decking started and progressing well from the south side heading north. Square columns from ground to level 2 formed and stripped
Everhome Markham Construction
Everhome Markham Construction
Everhome Markham Construction
March 8th
  –  
Decking for units N101 and N02 on the elevated portion of the NORTH Block has been completed. Rebar placement has started and continues.
Everhome Markham Construction
Everhome Markham Construction
Everhome Markham Construction
March 6th
  –  
Scaffolding to the second level of the EAST Block started
Everhome Markham Construction
Everhome Markham Construction
Everhome Markham Construction

January 2024

January 30th
  –  
Portion of the ground floor slab completed on the EAST Block
Everhome Markham Construction
Everhome Markham Construction
Everhome Markham Construction

December 2023

December 11th
  –  
Conduit work and top bar placement continues along the south side of the Central Courtyard in preparation for the next pour
Everhome Markham Construction
Everhome Markham Construction
Everhome Markham Construction
December 8th
  –  
First pour of the South Block ground floor section is complete
Everhome Markham Construction
Everhome Markham Construction
Everhome Markham Construction
December 6th
  –  
Rebar and Stud Rail placement continues on the Southwest side of Everhome
Everhome Markham Construction
Everhome Markham Construction
Everhome Markham Construction

November 2023

November 20th
  –  
Slab for the Southwest corner has been completed
Everhome Markham Construction
Everhome Markham Construction
Everhome Markham Construction

October 2023

October 27th
  –  
Decking on the West side continues for the ground floor slab
Everhome Markham Construction
Everhome Markham Construction
Everhome Markham Construction
October 25th
  –  
Decking work continues on the Ground Floor around the crane base
Everhome Markham Construction
Everhome Markham Construction
Everhome Markham Construction
October 2nd
  –  
Stripping of the Stairwell and EAST Block Elevators completed
Everhome Markham Construction
Everhome Markham Construction
Everhome Markham Construction

September 2023

September 26th
  –  
Structural slab along the north side, mid-span formed, next to the ramp on the south section
Everhome Markham Construction
Everhome Markham Construction
Everhome Markham Construction
September 22nd
  –  
Rebar placement continues to the garage door entry below the North Block
Everhome Markham Construction
Everhome Markham Construction
Everhome Markham Construction
September 18th
  –  
Decking, rebar and conduit placement continues along the Northeast side of the site
Everhome Markham Construction
Everhome Markham Construction
Everhome Markham Construction
September 8th
  –  
P1 structural slab poured from N6 to N9 (west to east), along the North Perimeter Wall, south to the Geo-Thermal wall
Everhome Markham Construction
Everhome Markham Construction
Everhome Markham Construction
September 6th
  –  
Aerial view capturing site progress at Everhome Markham
Everhome Markham Construction
Facing South
Everhome Markham Construction
Facing North
September 5th
  –  
Rebar and conduit work continues on the structural slab next to the North Perimeter Wall
Everhome Markham Construction
Everhome Markham Construction
Everhome Markham Construction
September 1st
  –  
North Perimeter Wall stripped and moved east for the next section
Everhome Markham Construction
Everhome Markham Construction
Everhome Markham Construction

August 2023

August 30th
  –  
Central section form work started, P1 to Ground
Everhome Markham Construction
Everhome Markham Construction
Everhome Markham Construction
August 29th
  –  
P1 decking continues along the northern side of the property from West to East
Everhome Markham Construction
Everhome Markham Construction
Everhome Markham Construction
August 28th
  –  
P1 Structural Slab poured that will act as base for the soil in the Central Courtyard
Everhome Markham Construction
Everhome Markham Construction
Everhome Markham Construction
August 4th
  –  
All SOG (Slab On Grade) now complete!
Everhome Markham Construction
Everhome Markham Construction
Everhome Markham Construction
August 2nd
  –  
Prepping for Concrete Pour at P1 around the crane base
Everhome Markham Construction
Everhome Markham Construction
Everhome Markham Construction

July 2023

July 26th
  –  
Completed Slab On Grade (SOG) between the North perimeter wall and the Geo-thermal Room
Everhome Markham Construction
Everhome Markham Construction
Everhome Markham Construction
July 18th
  –  
Additional 3/4” stone received for spreading in preparation of Slab On Grade (SOG) around the crane base
Everhome Markham Construction
Everhome Markham Construction
Everhome Markham Construction
July 13th
  –  
Conduit and rebar for the west side completed, awaiting concrete
Everhome Markham Construction
Everhome Markham Construction
Everhome Markham Construction
July 11th
  –  
Final geo-thermal loop complete and pressure tested. Trenches with the main loop pipes are being back filled with 3/4 stone
Everhome Markham Construction
Everhome Markham Construction
Everhome Markham Construction

June 2023

June 28th
  –  
The final geo-thermal loop (B) being grouted and cleared for fusing to begin
Everhome Markham Construction
Everhome Markham Construction
Everhome Markham Construction
June 19th
  –  
Erecting column forms from P1 to Ground on the South East side.
Everhome Markham Construction
Everhome Markham Construction
Everhome Markham Construction
June 14th
  –  
Perimeter wall forms have arrived to site
Everhome Markham Construction
Everhome Markham Construction
Everhome Markham Construction

April 2023

April 20th
  –  
Formwork for P2 Structural Slab underway
Everhome Markham Construction
Everhome Markham Construction
Everhome Markham Construction
April 14th
  –  
Pour 2 on P3 completed
Everhome Markham Construction
Everhome Markham Construction
Everhome Markham Construction
April 13th
  –  
Slab On Grade (SOG) P3 Pour 1 completed
Everhome Markham Construction
Everhome Markham Construction
Everhome Markham Construction
April 4th
  –  
3/4" stone now being distributed on P3 in advance of Slab-On-Grade
Everhome Markham Construction
Everhome Markham Construction
Everhome Markham Construction

March 2023

March 29th
  –  
Final preparation for Slab on Grade
Everhome Markham Construction
Everhome Markham Construction
Everhome Markham Construction

February 2023

February 28th
  –  
East end of geo-thermal room completed
Everhome Markham Construction
Everhome Markham Construction
Everhome Markham Construction

January 2023

January 23rd
  –  
Geo-thermal room perimeter on P3 is complete
Everhome Markham Construction
Everhome Markham Construction
Everhome Markham Construction

December 2022

December 7th
  –  
P3 Termination Wall Connected to Geo-thermal Room Wall
Everhome Markham Construction
Everhome Markham Construction

November 2022

November 24th
  –  
Preparing Forms for the Geo-thermal Room
Everhome Markham Construction
Everhome Markham Construction

October 2022

October 19th
  –  
CRANE BASE COMPLETE
Everhome Markham Construction
Everhome Markham Construction

September 2022

September 16th
  –  
Second Row of Cross Braces Installed on the Northwest Corner.
Everhome Markham Construction
Everhome Markham Construction

August 2022

August 18th
  –  
Excavation Reinitiated to Reach the Final Geodetic Depth.
Everhome Markham Construction
Everhome Markham Construction

July 2022

July 15th
  –  
Excavation and lagging work continues...
Everhome Markham Construction
Everhome Markham Construction

June 2022

June 10th
  –  
86 Shoring Piles Complete.
Everhome Markham Construction
Everhome Markham Construction

May 2022

May 5th
  –  
Fourteen piles completed to date on the north side.
Everhome Markham Construction
Everhome Markham Construction

April 2022 – Official Start of Construction

April 23th
  –  
Completing the platform for shoring to begin.
Everhome Markham Construction
Everhome Markham Construction

March 2022

March 21st
  –  
Geo-thermal drilling has been completed.
Everhome Markham Construction
Everhome Markham Construction


February 2022

February 24th
  –  
Bore hole drilling continues.
Everhome Markham Construction
Everhome Markham Construction


January 2022

January 2022
Everhome Markham Construction
Everhome Markham Construction


October 2021

October 2021
Everhome Markham Construction
Everhome Markham Construction


July 2021

July 2021
Everhome Markham Construction


June 2021

June 2021
Everhome Markham Construction
Everhome Markham Construction
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
View Looking North
X
View Looking Northeast
X
View Looking Northeast
X
Excavation and lagging work continues...
X
Excavation and lagging work continues...
X
Excavation and lagging work continues...
X
Excavation and lagging work continues...
X
Excavation and lagging work continues...
X
Excavation and lagging work continues...
X
Excavation and lagging work continues...
X
Excavation and lagging work continues...
X
Excavation and lagging work continues...
X
Excavation and lagging work continues...
X
Excavation and lagging work continues...
X
Excavation and lagging work continues...
X
Excavation and lagging work continues...
X
Excavation and lagging work continues...
X
Excavation and lagging work continues...
X
Test tiebacks have been approved.
X
Shaving of caissons on the west side underway.
X
Test tiebacks have been approved.
X
North Side Wood Fence Complete. Tieback Placement Continues.
X
North Side Wood Fence Complete. Tieback Placement Continues.
X
North Side Wood Fence Complete. Tieback Placement Continues.
X
Southwest View of the Construction Site at Everhome.
X
Lagging Work at the Entrance Along the East Side.
X
Tieback Installation Continues on the South Side.
X
All Tiebacks are Complete. Additional Excavation has Started.
X
All Tiebacks are Complete. Additional Excavation has Started.
X
All Tiebacks are Complete. Additional Excavation has Started.
X
Excavation Reinitiated to Reach the Final Geodetic Depth.
X
Excavation Reinitiated to Reach the Final Geodetic Depth.
X
Excavation Reinitiated to Reach the Final Geodetic Depth.
X
NOW UNDER CONSTRUCTION: Continuing with Excavation and Tieback Welding to Reach Final Depth.
X
NOW UNDER CONSTRUCTION: Continuing with Excavation and Tieback Welding to Reach Final Depth.
X
NOW UNDER CONSTRUCTION: Continuing with Excavation and Tieback Welding to Reach Final Depth.
X
UNDER CONSTRUCTION: Lagging and Excavation is Ongoing
X
UNDER CONSTRUCTION: Lagging and Excavation is Ongoing
X
UNDER CONSTRUCTION: Lagging and Excavation is Ongoing
X
UNDER CONSTRUCTION: Lagging and Excavation is Ongoing
X
UNDER CONSTRUCTION: Lagging and Excavation is Ongoing
X
UNDER CONSTRUCTION: Lagging and Excavation is Ongoing
X
Installation of Walers And Lagging Work Continues
X
Installation of Walers And Lagging Work Continues
X
Installation of Walers And Lagging Work Continues
X
Trench Cutting to Complete Lagging on South Side.
X
Trench Cutting to Complete Lagging on South Side.
X
Trench Cutting to Complete Lagging on South Side.
X
Second Row of Cross Braces Installed on the Northwest Corner.
X
Additional Lagging Below Tiebacks on Northwest side.
X
Additional Lagging Below Tiebacks on Northwest side.
X
Southwest Corner, Shaving of Piles Continues.
X
Bulk Excavation Ongoing.
X
Bulk Excavation Continues.
X
Southwest Corner, Shaving of Piles Continues to Allow for Second Cross Braces.
X
Bulk Excavation Continues.
X
Bulk Excavation Continues.
X
Preparation for Rakers and Raker Pad Underway.
X
Preparation for Rakers and Raker Pad Underway.
X
2nd row of Corner Braces on the Southwest Side completed.
X
Excavating for Crane Pad.
X
Excavating for Crane Pad.
X
Excavating for Crane Pad.
X
Crane Base Installation Started
X
Crane Base Installation Started
X
Crane Base Installation Started
X
CRANE BASE COMPLETE
X
CRANE BASE COMPLETE
X
CRANE BASE COMPLETE
X
CRANE NOW ERECTED
X
CRANE NOW ERECTED
X
CRANE NOW ERECTED
X
Overall Site Progress
X
Verticals Formed with Footings in Place on P3 Level
X
Waterproofing of P3
X
Preparing forms for additional verticals for P3 Level
X
Water proofing the southwest corner, followed by rebar placement and the footings to allow the erection of the perimeter walls
X
Demising wall at the end of P3 to P2 level, formed and completed
X
Detailed excavation for footings on north side of P3
X
Footing forms for P3 Mechanical and Geo-thermal Rooms
X
Trenching for central area footings on P3
X
Preparing Forms for the Geo-thermal Room
X
Additional Vertical Forms Prepped on P3
X
View looking east showing progress of footings and verticals
X
P3 Termination Wall Connected to Geo-thermal Room Wall
X
Waterproofing Started on the East Side
X
Wall Forms Erected on the South Side
X
Waterproofing and rebar in place for formwork on the southeast corner.
X
P3 verticals are all completed, showing rackers and cross braces on the northwest side.
X
Two P2 verticals erected, waterproofing and rebar in place on south side.
X
Forming perimeter walls on the south and east sides.
X
Forming the north wall of the geo-thermal room on P3.
X
Placing rebar in front of waterproofing on the south side.
X
Geo-thermal room perimeter on P3 is complete
X
Rebar for P2 verticals have been assembled
X
Forming of the sump pit for the east block has started
X
New wall formed on P2
X
Main sump pit for East Block installed and surrounded by U-Fill
X
Walls formed on P2
X
Geo-thermal work on P3 continues
X
Geo-thermal room strip footings extended and forms for walls are being erected
X
Bore holes repaired and being connected on P3 level
X
Strip footings and north side wall forms continue for geo-thermal room
X
Geo-thermal work on P3 continues
X
Eastern edge of the geo-thermal room and applicable strip footings
X
East end of geo-thermal room completed
X
Remaining lagging work on northeast side now continues
X
Waterproofing on P3 to P2 Demising wall complete
X
Bore hole circuits penetrated into geo-thermal room
X
Bore holes connected to the main circuit loop
X
Circuit loops positioned in trenches under P3
X
Final preparation for Slab on Grade
X
Final preparation for Slab on Grade
X
Final preparation for Slab on Grade
X
3/4" stone now being distributed on P3 in advance of Slab-On-Grade
X
3/4" stone now being distributed on P3 in advance of Slab-On-Grade
X
3/4" stone now being distributed on P3 in advance of Slab-On-Grade
X
Slab On Grade (SOG) P3 Pour 1 completed
X
P3 Level, Preparation of Pour 2 in the foreground and completed Pour 1 in the distance
X
P3 Pour 2 sub-grade preparation complete
X
Pour 2 on P3 completed
X
Pour 2 on P3 completed
X
Pour 2 on P3 completed
X
Formwork for P2 Structural Slab underway
X
Geo-thermal circuit D loop is being laid on P2 trenches
X
Formwork for P2 capitals on columns underway
X
Perimeter wall forms have arrived to site
X
North Block east stair well, footings being poured
X
South East side perimeter wall rebar placement has started
X
Erecting column forms from P1 to Ground on the South East side.
X
Detailed excavation for EAST Block Elevator Pit ready to receive the pre-formed rebar assembly (shown in the image)
X
Erecting north wall form above Geo-Thermal Room from P2 to P1
X
The final geo-thermal loop (B) being grouted and cleared for fusing to begin
X
Perimeter wall forms in place for the Northside of the site at the retaining wall, P1 to ground
X
Rebar placement around the east stairwell for the North Block started, Level 2 to 1. Trenching for the geo-thermal loops in the foreground
X
Final geo-thermal loop complete and pressure tested. Trenches with the main loop pipes are being back filled with 3/4 stone
X
Stone also being spread out over the remaining sections in preparation for Slab On Grade (SOG)
X
Cross braces on the southwest corner cut and being removed
X
Conduit and rebar for the west side completed, awaiting concrete
X
Strip footings on the north and east side poured. All footings are now complete at Everhome
X
West side structural slab fully poured
X
Additional 3/4” stone received for spreading in preparation of Slab On Grade (SOG) around the crane base
X
P2 Level Waterproofing on the north side completed. Now preparing for rebar placement for the perimeter wall
X
Rebar work continues on the southeast side, from P1 to Ground
X
Completed Slab On Grade (SOG) between the North perimeter wall and the Geo-thermal Room
X
Preparation to initiate shotcrete along the North perimeter wall, towards the East perimeter wall
X
Completed Slab On Grade (SOG) around the crane base
X
Prepping for Concrete Pour at P1 around the crane base
X
Waterproofing progressing along the North Wall, heading eastwards
X
Spreading stone in preparation of the Slab On Grade (SOG) for the North East portion
X
August 4th - All SOG (Slab On Grade) now complete!
X
August 4th - All SOG (Slab On Grade) now complete!
X
August 4th - All SOG (Slab On Grade) now complete!
X
August 28th - P1 Structural Slab poured that will act as base for the soil in the Central Courtyard
X
August 28th - Waterproofing on the East Perimeter Wall started, P1 to Ground
X
August 28th - Rebar installed for the North and East Perimeter Wall Sections showcasing the duct bank for Electrical Utility on the East Face
X
August 29th - P1 decking continues along the northern side of the property from West to East
X
August 29th - Perimeter Wall of the North and East sections completed, P1 to Ground
X
August 29th - South Perimeter Wall Forms are starting to be placed from the east side, P1 to Ground
X
August 30th - Central section form work started, P1 to Ground
X
August 30th - Southwest Air Exhaust forming started, P1 to Ground
X
August 30th - Stripping of the South Perimeter wall at the East Side, P1 to Ground
X
September 1st - North Perimeter Wall stripped and moved east for the next section
X
September 1st - Tie rods welded to the East Perimeter wall piles
X
September 1st - Central interior wall around the crane base formed from P1 to Ground
X
September 5th - Rebar and conduit work continues on the structural slab next to the North Perimeter Wall
X
September 5th - Decking for P1 structural slab continues along the northern side of the site
X
September 5th - Rebar placement on the East Perimeter Wall continues, from P1 to Ground
X
September 6th - Aerial view capturing site progress at Everhome Markham
X
September 6th - Aerial view capturing site progress at Everhome Markham
X
September 8th - P1 structural slab poured from N6 to N9 (west to east), along the North Perimeter Wall, south to the Geo-Thermal wall
X
September 8th - Rebar along the East Perimeter Wall complete for shotcrete application, P1 to Ground
X
September 8th - Stripping of the forms for the southwest corner air shaft, P1 to Ground
X
September 18th - Decking, rebar and conduit placement continues along the Northeast side of the site
X
September 18th - Shotcrete used to complete the Southeast corner and the entire East Perimeter Wall
X
September 18th - Structural slab pour on the north east
X
September 22nd - Rebar placement continues to the garage door entry below the North Block
X
September 22nd - Structural slab pour on the Northside of the P1 Ramp
X
September 22nd - Piping installation continues below grade, P3 and P2
X
September 26th - Structural slab along the north side, mid-span formed, next to the ramp on the south section
X
September 26th - Bottom rebar placement continues and conduit work started along the Northeast side for ground floor slab
X
September 26th - Forms are being placed around the EAST BLOCK elevators
X
October 2nd - Stripping of the Stairwell and EAST Block Elevators completed
X
October 2nd - Deck forming for the Northeast corner complete and rebar placement continues
X
October 2nd - Extensive rebar placement continues for the northeast area in anticipation of Gas Connection
X
October 25th - Decking work continues on the Ground Floor around the crane base
X
October 25th - Storm Water Tank deck continues on the Northwest side in preparation for Site Service Connections
X
October 25th - Northwest Perimeter wall forming continues to Ground Floor
X
October 27th - Decking on the West side continues for the ground floor slab
X
October 27th - Waterproofing, and rebar placement completed on the North side, in preparation for Shotcrete to follow
X
October 27th - Air shaft at the Northeast corner formed for the south and west walls
X
November 20th - Slab for the Southwest corner has been completed
X
November 20th - Decking completed between the Central Courtyard and South Block, ready to receive rebar and conduit
X
November 20th - Rebar and conduit work has started on the Southwest corner
X
December 6th - Rebar and Stud Rail placement continues on the Southwest side of Everhome
X
December 6th - Wall forms and rebar in place for Storm Water Tank pour
X
December 6th - North perimeter wall Shotcrete completed
X
December 8th - First pour of the South Block ground floor section is complete
X
December 8th - Shotcrete wall stripped along the Northside of the site
X
December 8th - Stormceptor area within the Storm Water Tank completed on the Westside of the site
X
December 11th - Conduit work and top bar placement continues along the south side of the Central Courtyard in preparation for the next pour
X
December 11th - Completed the second concrete pour for the terraces related to the SOUTH Block
X
December 11th - Bottom rebar placement on the last portion of the east side of the SOUTH Block underway
X
January 30th - Portion of the ground floor slab completed on the EAST Block
X
January 30th - Additional portions of the ground floor slab to the north side of the EAST Block completed
X
January 30th - Wall form erected to pour the north side of the fire route which also encases the long term bicycle storage for homeowners at grade
X
March 6th - Scaffolding to the second level of the EAST Block started
X
March 6th - NORTH Block poured the terraces along the northern property line
X
March 6th - EAST Block retail mezzanine decking complete and rebar work started. Stair well east of the mezzanine level formed to the second level
X
March 8th - Decking for units N101 and N02 on the elevated portion of the NORTH Block has been completed. Rebar placement has started and continues
X
March 8th - Rebar placement complete up to Level 2 for Stair E on the EAST Block. Exterior formwork around the rebar to follow next, before pouring concrete
X
March 8th - Rebar placement complete up to Level 2 for Elevator 2 in the SOUTH Block. Exterior formwork to follow around the rebar, before pouring concrete
X
March 18th - EAST Block, level 2 decking started and progressing well from the south side heading north. Square columns from ground to level 2 formed and stripped
X
March 18th - Concrete pour for the lower sections related to N101 and N102 completed
X
March 18th - Rebar placement for the top section well underway with intentions to pour concrete this week
X
March 22nd - N101 and N102 top concrete pour completed
X
March 22nd - Bottom pour associated with the NORTH Block, entrance of N101 and N02 completed. Forms erected for the top concrete pour
X
March 22nd - Forms stripped to expose columns from Ground to Level 2 on the EAST Block
X