Construction Update
Click on images below
September 2023
September 26th – Structural slab along the north side, mid-span formed, next to the ramp on the south section



September 22nd – Rebar placement continues to the garage door entry below the North Block



September 18th – Decking, rebar and conduit placement continues along the Northeast side of the site



September 8th – P1 structural slab poured from N6 to N9 (west to east), along the North Perimeter Wall, south to the Geo-Thermal wall



September 6th – Aerial view capturing site progress at Everhome Markham


September 5th – Rebar and conduit work continues on the structural slab next to the North Perimeter Wall



September 1st – North Perimeter Wall stripped and moved east for the next section



August 2023
August 30th – Central section form work started, P1 to Ground



August 29th – P1 decking continues along the northern side of the property from West to East



August 28th – P1 Structural Slab poured that will act as base for the soil in the Central Courtyard



August 4th – All SOG (Slab On Grade) now complete!



August 2nd – Prepping for Concrete Pour at P1 around the crane base



July 2023
July 26th – Completed Slab On Grade (SOG) between the North perimeter wall and the Geo-thermal Room



July 18th – Additional 3/4” stone received for spreading in preparation of Slab On Grade (SOG) around the crane base



July 13th – Conduit and rebar for the west side completed, awaiting concrete



July 11th – Final geo-thermal loop complete and pressure tested. Trenches with the main loop pipes are being back filled with 3/4 stone



June 2023
June 28th – The final geo-thermal loop (B) being grouted and cleared for fusing to begin



June 19th – Erecting column forms from P1 to Ground on the South East side.



June 14th – Perimeter wall forms have arrived to site



April 2023
April 20th – Formwork for P2 Structural Slab underway



April 14th – Pour 2 on P3 completed



April 13th – Slab On Grade (SOG) P3 Pour 1 completed



April 4th – 3/4" stone now being distributed on P3 in advance of Slab-On-Grade
March 2023
March 29th – Final preparation for Slab on Grade
February 2023
February 28th – East end of geo-thermal room completed
January 2023
January 23rd – Geo-thermal room perimeter on P3 is complete
December 2022
December 7th – P3 Termination Wall Connected to Geo-thermal Room Wall
November 2022
November 24th – Preparing Forms for the Geo-thermal Room
October 2022
October 19th – CRANE BASE COMPLETE
September 2022
September 16th – Second Row of Cross Braces Installed on the Northwest Corner.
August 2022
August 18th – Excavation Reinitiated to Reach the Final Geodetic Depth.
July 2022
July 15th – Excavation and lagging work continues...
June 2022
June 10th – 86 Shoring Piles Complete.
May 2022
May 5th – Fourteen piles completed to date on the north side.
April 2022 – Official Start of Construction
April 23th – Completing the platform for shoring to begin.
March 2022
March 21st – Geo-thermal drilling has been completed.
February 2022
February 24th – Bore hole drilling continues.
January 2022
January 2022
October 2021
October 2021
July 2021
July 2021
June 2021
June 2021