Construction Update

Click on images below

March 2023

March 22nd
  –  
Bore hole circuits penetrated into geo-thermal room
Everhome Markham Construction
Everhome Markham Construction
Everhome Markham Construction

February 2023

February 28th
  –  
East end of geo-thermal room completed
Everhome Markham Construction
Everhome Markham Construction
Everhome Markham Construction
February 15th
  –  
Strip footings and north side wall forms continue for geo-thermal room
Everhome Markham Construction
Everhome Markham Construction
Everhome Markham Construction
February 14th
  –  
Geo-thermal work on P3 continues
Everhome Markham Construction
Everhome Markham Construction
Everhome Markham Construction
February 7th
  –  
New wall formed on P2
Everhome Markham Construction
Everhome Markham Construction
Everhome Markham Construction

January 2023

January 23rd
  –  
Geo-thermal room perimeter on P3 is complete
Everhome Markham Construction
Everhome Markham Construction
Everhome Markham Construction

December 2022

December 7th
  –  
P3 Termination Wall Connected to Geo-thermal Room Wall
Everhome Markham Construction
Everhome Markham Construction
Everhome Markham Construction

November 2022

November 24th
  –  
Preparing Forms for the Geo-thermal Room
Everhome Markham Construction
Everhome Markham Construction
Everhome Markham Construction

October 2022

October 19th
  –  
CRANE BASE COMPLETE
Everhome Markham Construction
Everhome Markham Construction
Everhome Markham Construction

September 2022

September 16th
  –  
Second Row of Cross Braces Installed on the Northwest Corner.
Everhome Markham Construction
Everhome Markham Construction
Everhome Markham Construction

August 2022

August 18th
  –  
Excavation Reinitiated to Reach the Final Geodetic Depth.
Everhome Markham Construction
Everhome Markham Construction
Everhome Markham Construction

July 2022

July 15th
  –  
Excavation and lagging work continues...
Everhome Markham Construction
Everhome Markham Construction
Everhome Markham Construction

June 2022

June 10th
  –  
86 Shoring Piles Complete.
Everhome Markham Construction
Everhome Markham Construction
Everhome Markham Construction

May 2022

May 27th
  –  
Shoring activities continue on the north side, next to the Radiant Montessori School.
Everhome Markham Construction

April 2022

April 23th
  –  
Completing the platform for shoring to begin.
Everhome Markham Construction
Everhome Markham Construction

March 2022

March 24th
  –  
Platform preparation at Everhome Markham underway.
Everhome Markham Construction


February 2022

February 24th
  –  
Bore hole drilling continues.
Everhome Markham Construction
Everhome Markham Construction


January 2022

January 2022
Everhome Markham Construction
Everhome Markham Construction


October 2021

October 2021
Everhome Markham Construction
Everhome Markham Construction


July 2021

July 2021
Everhome Markham Construction


June 2021

June 2021
Everhome Markham Construction
Everhome Markham Construction
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
View Looking North
X
View Looking Northeast
X
View Looking Northeast
X
Excavation and lagging work continues...
X
Excavation and lagging work continues...
X
Excavation and lagging work continues...
X
Excavation and lagging work continues...
X
Excavation and lagging work continues...
X
Excavation and lagging work continues...
X
Excavation and lagging work continues...
X
Excavation and lagging work continues...
X
Excavation and lagging work continues...
X
Excavation and lagging work continues...
X
Excavation and lagging work continues...
X
Excavation and lagging work continues...
X
Excavation and lagging work continues...
X
Excavation and lagging work continues...
X
Excavation and lagging work continues...
X
Test tiebacks have been approved.
X
Shaving of caissons on the west side underway.
X
Test tiebacks have been approved.
X
North Side Wood Fence Complete. Tieback Placement Continues.
X
North Side Wood Fence Complete. Tieback Placement Continues.
X
North Side Wood Fence Complete. Tieback Placement Continues.
X
Southwest View of the Construction Site at Everhome.
X
Lagging Work at the Entrance Along the East Side.
X
Tieback Installation Continues on the South Side.
X
All Tiebacks are Complete. Additional Excavation has Started.
X
All Tiebacks are Complete. Additional Excavation has Started.
X
All Tiebacks are Complete. Additional Excavation has Started.
X
Excavation Reinitiated to Reach the Final Geodetic Depth.
X
Excavation Reinitiated to Reach the Final Geodetic Depth.
X
Excavation Reinitiated to Reach the Final Geodetic Depth.
X
NOW UNDER CONSTRUCTION: Continuing with Excavation and Tieback Welding to Reach Final Depth.
X
NOW UNDER CONSTRUCTION: Continuing with Excavation and Tieback Welding to Reach Final Depth.
X
NOW UNDER CONSTRUCTION: Continuing with Excavation and Tieback Welding to Reach Final Depth.
X
UNDER CONSTRUCTION: Lagging and Excavation is Ongoing
X
UNDER CONSTRUCTION: Lagging and Excavation is Ongoing
X
UNDER CONSTRUCTION: Lagging and Excavation is Ongoing
X
UNDER CONSTRUCTION: Lagging and Excavation is Ongoing
X
UNDER CONSTRUCTION: Lagging and Excavation is Ongoing
X
UNDER CONSTRUCTION: Lagging and Excavation is Ongoing
X
Installation of Walers And Lagging Work Continues
X
Installation of Walers And Lagging Work Continues
X
Installation of Walers And Lagging Work Continues
X
Trench Cutting to Complete Lagging on South Side.
X
Trench Cutting to Complete Lagging on South Side.
X
Trench Cutting to Complete Lagging on South Side.
X
Second Row of Cross Braces Installed on the Northwest Corner.
X
Additional Lagging Below Tiebacks on Northwest side.
X
Additional Lagging Below Tiebacks on Northwest side.
X
Southwest Corner, Shaving of Piles Continues.
X
Bulk Excavation Ongoing.
X
Bulk Excavation Continues.
X
Southwest Corner, Shaving of Piles Continues to Allow for Second Cross Braces.
X
Bulk Excavation Continues.
X
Bulk Excavation Continues.
X
Preparation for Rakers and Raker Pad Underway.
X
Preparation for Rakers and Raker Pad Underway.
X
2nd row of Corner Braces on the Southwest Side completed.
X
Excavating for Crane Pad.
X
Excavating for Crane Pad.
X
Excavating for Crane Pad.
X
Crane Base Installation Started
X
Crane Base Installation Started
X
Crane Base Installation Started
X
CRANE BASE COMPLETE
X
CRANE BASE COMPLETE
X
CRANE BASE COMPLETE
X
CRANE NOW ERECTED
X
CRANE NOW ERECTED
X
CRANE NOW ERECTED
X
Overall Site Progress
X
Verticals Formed with Footings in Place on P3 Level
X
Waterproofing of P3
X
Preparing forms for additional verticals for P3 Level
X
Water proofing the southwest corner, followed by rebar placement and the footings to allow the erection of the perimeter walls
X
Demising wall at the end of P3 to P2 level, formed and completed
X
Detailed excavation for footings on north side of P3
X
Footing forms for P3 Mechanical and Geo-thermal Rooms
X
Trenching for central area footings on P3
X
Preparing Forms for the Geo-thermal Room
X
Additional Vertical Forms Prepped on P3
X
View looking east showing progress of footings and verticals
X
P3 Termination Wall Connected to Geo-thermal Room Wall
X
Waterproofing Started on the East Side
X
Wall Forms Erected on the South Side
X
Waterproofing and rebar in place for formwork on the southeast corner.
X
P3 verticals are all completed, showing rackers and cross braces on the northwest side.
X
Two P2 verticals erected, waterproofing and rebar in place on south side.
X
Forming perimeter walls on the south and east sides.
X
Forming the north wall of the geo-thermal room on P3.
X
Placing rebar in front of waterproofing on the south side.
X
Geo-thermal room perimeter on P3 is complete
X
Rebar for P2 verticals have been assembled
X
Forming of the sump pit for the east block has started
X
New wall formed on P2
X
Main sump pit for East Block installed and surrounded by U-Fill
X
Walls formed on P2
X
Geo-thermal work on P3 continues
X
Geo-thermal room strip footings extended and forms for walls are being erected
X
Bore holes repaired and being connected on P3 level
X
Strip footings and north side wall forms continue for geo-thermal room
X
Geo-thermal work on P3 continues
X
Eastern edge of the geo-thermal room and applicable strip footings
X
East end of geo-thermal room completed
X
Remaining lagging work on northeast side now continues
X
Waterproofing on P3 to P2 Demising wall complete
X
Bore hole circuits penetrated into geo-thermal room
X
Bore holes connected to the main circuit loop
X
Circuit loops positioned in trenches under P3
X