Construction Update
Click on image to enlarge
August 2025
August 10th – Everhome Markham Community Updates






August 7th – NORTH BLOCK: North Block lobby is shown along with suites east of the lobby.

July 2025
July 31st Updates






July 29th – Exterior West Elevation



July 17th – EAST BLOCK: West side exterior waterproofing and cladding progressing well.



July 4th – The angular archway entrance to the North block completed and ready to receive Prada Lime Green aluminium metal plate.



May 2025
May 27th – NORTH and SOUTH Blocks: Demising Wall steel stud framing in place for level 2.



April 2025
April 17th – NORTH Block: Roof Pour Underway.



April 14th – All Windows on East Block Now Completed.



April 8th



April 4th



April 1st



March 2025
March 21st – NORTH Block: 5th level slab pour completed.



March 19th – EAST Block: Waterproofing of the Penthouse Level Terraces almost complete.



February 2025
February 21st – EAST Block : Generator placed in its final position on the roof. Mechanical penthouse room, steel stud and sheathing well underway.



January 2025
January 20th – EAST Block built form facing east onto McCowan Rd.



December 2024
December 18th – EAST Block formwork completed to the roof of the mechanical penthouse to the east side and the rooftop terraces of the west side two-storey units. Windows installation completed to Level 7.



November 2024
November 5th – Window installation for Levels 2 and 3 completed



October 2024
October 24th – Decking for the Roof of the 2-Storey Penthouse Suites facing West well underway. Elevator and south stair well already erected to the Mechanical Penthouse Level.



September 2024
September 13th – EAST Block : Level 8 pour 1, completed, view looking East



August 2024
August 29th – Decking South Block Level 2



May 2024
May 31st – EAST BLOCK : 40% Level 3 Slab Completed



March 2024
March 22nd – N101 and N102 top concrete pour completed



December 2023
December 11th – Conduit work and top bar placement continues along the south side of the Central Courtyard in preparation for the next pour



October 2023
October 27th – Decking on the West side continues for the ground floor slab



September 2023
September 26th – Structural slab along the north side, mid-span formed, next to the ramp on the south section



July 2023
July 26th – Completed Slab On Grade (SOG) between the North perimeter wall and the Geo-thermal Room



June 2023
June 28th – The final geo-thermal loop (B) being grouted and cleared for fusing to begin



April 2023
April 20th – Formwork for P2 Structural Slab underway



February 2023
February 28th – East end of geo-thermal room completed
January 2023
January 23rd – Geo-thermal room perimeter on P3 is complete
December 2022
December 7th – P3 Termination Wall Connected to Geo-thermal Room Wall
November 2022
November 24th – Preparing Forms for the Geo-thermal Room
October 2022
October 19th – CRANE BASE COMPLETE
August 2022
August 18th – Excavation Reinitiated to Reach the Final Geodetic Depth.
July 2022
July 15th – Excavation and lagging work continues...
June 2022
June 10th – 86 Shoring Piles Complete.
May 2022
May 5th – Fourteen piles completed to date on the north side.
April 2022 – Official Start of Construction
April 23th – Completing the platform for shoring to begin.
February 2022
February 24th – Bore hole drilling continues.
January 2022
January 2022
October 2021
October 2021
July 2021
July 2021
June 2021
June 2021
