Construction Update

Click on images below

August 2022

August 9th
  –  
Tiebacks 50% Complete. Additional Excavation to Follow.
Everhome Markham Construction
Everhome Markham Construction
Everhome Markham Construction

July 2022

July 29th
  –  
North Side Wood Fence Complete. Tieback Placement Continues.
Everhome Markham Construction
Everhome Markham Construction
Everhome Markham Construction
July 27th
  –  
Test tiebacks have been approved. Shaving of caissons on the west side underway.
Everhome Markham Construction
Everhome Markham Construction
Everhome Markham Construction
July 22nd
  –  
Excavation and lagging work continues...
Everhome Markham Construction
Everhome Markham Construction
Everhome Markham Construction
July 15th
  –  
Excavation and lagging work continues...
Everhome Markham Construction
Everhome Markham Construction
Everhome Markham Construction
July 11th
  –  
Excavation and lagging work continues...
Everhome Markham Construction
Everhome Markham Construction
Everhome Markham Construction
July 7th
  –  
Excavation and lagging work continues...
Everhome Markham Construction
Everhome Markham Construction
Everhome Markham Construction
July 6th
  –  
Excavation and lagging work continues...
Everhome Markham Construction
Everhome Markham Construction
Everhome Markham Construction

June 2022

June 28th
  –  
Excavation Started!
Everhome Markham Construction
Everhome Markham Construction
Everhome Markham Construction
June 27th
  –  
All shoring piles now complete. EXCAVATION STARTING!
Everhome Markham Construction
June 21st
  –  
149 Shoring Piles are Now Completed. Excavation to Begin.
Everhome Markham Construction
Everhome Markham Construction
Everhome Markham Construction
June 15th
  –  
120 of 149 Shoring Piles Now Completed.
Everhome Markham Construction
Everhome Markham Construction
Everhome Markham Construction
June 10th
  –  
86 Shoring Piles Complete.
Everhome Markham Construction
Everhome Markham Construction
Everhome Markham Construction
June 2nd
  –  
61 Total Piles Completed to date.
Everhome Markham Construction
Everhome Markham Construction
Everhome Markham Construction

May 2022

May 31th
  –  
40 piles completed to date - Shoring moving well!
Everhome Markham Construction
May 27th
  –  
Shoring activities continue on the north side, next to the Radiant Montessori School.
Everhome Markham Construction
May 5th
  –  
Fourteen piles completed to date on the north side.
Everhome Markham Construction
Everhome Markham Construction

April 2022

April 29th
  –  
Ten piles completed to date on the north side.
Everhome Markham Construction
Everhome Markham Construction
April 28th
  –  
Six piles completed on the northwest side.
Everhome Markham Construction
Everhome Markham Construction
April 27th
  –  
Shoring work has started. Two piles completed on the north side.
Everhome Markham Construction
Everhome Markham Construction
April 23th
  –  
Completing the platform for shoring to begin.
Everhome Markham Construction
Everhome Markham Construction
April 18th
  –  
Platform for shoring almost complete.
Everhome Markham Construction
Everhome Markham Construction
April 12th
  –  
Platform preparation continues.
Everhome Markham Construction
Everhome Markham Construction
April 4th
  –  
Geothermal drilling has been completed.
Everhome Markham Construction
Everhome Markham Construction

March 2022

March 24th
  –  
Platform preparation at Everhome Markham underway.
Everhome Markham Construction


February 2022

February 24th
  –  
Bore hole drilling continues.
Everhome Markham Construction
Everhome Markham Construction


January 2022

January 2022
Everhome Markham Construction
Everhome Markham Construction


October 2021

October 2021
Everhome Markham Construction
Everhome Markham Construction


July 2021

July 2021
Everhome Markham Construction


June 2021

June 2021
Everhome Markham Construction
Everhome Markham Construction
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
View Looking North
X
View Looking Northeast
X
View Looking Northeast
X
Excavation and lagging work continues...
X
Excavation and lagging work continues...
X
Excavation and lagging work continues...
X
Excavation and lagging work continues...
X
Excavation and lagging work continues...
X
Excavation and lagging work continues...
X
Excavation and lagging work continues...
X
Excavation and lagging work continues...
X
Excavation and lagging work continues...
X
Excavation and lagging work continues...
X
Excavation and lagging work continues...
X
Excavation and lagging work continues...
X
Excavation and lagging work continues...
X
Excavation and lagging work continues...
X
Excavation and lagging work continues...
X
Test tiebacks have been approved.
X
Shaving of caissons on the west side underway.
X
Test tiebacks have been approved.
X
North Side Wood Fence Complete. Tieback Placement Continues.
X
North Side Wood Fence Complete. Tieback Placement Continues.
X
North Side Wood Fence Complete. Tieback Placement Continues.
X
Southwest View of the Construction Site at Everhome.
X
Lagging Work at the Entrance Along the East Side.
X
Tieback Installation Continues on the South Side.
X